An organization has a standardized change management plan that all project managers must adhere to. A project manager has worked with the Change Control Board in his organization to approve a change…

The correct answer is D. Update the WBS. Once a scope change is approved by the Change Control Board, the project manager must update the Work Breakdown Structure to reflect the new authorized scope.

Security Program Management & Governance

Question

An organization has a standardized change management plan that all project managers must adhere to. A project manager has worked with the Change Control Board in his organization to approve a change to project scope. What should the standardized change management plan require the project manager to do with the approved scope change?

Options

  • APerform risk assessment on the new change.
  • BCommunicate the change to the vendor.
  • CCreate a cost estimate for the change.
  • DUpdate the WBS.

How the community answered

(28 responses)
  • B
    4% (1)
  • D
    96% (27)

Why each option

Once a scope change is approved by the Change Control Board, the project manager must update the Work Breakdown Structure to reflect the new authorized scope.

APerform risk assessment on the new change.

Risk assessment is performed before submitting a change request for approval, not after the CCB has already approved it.

BCommunicate the change to the vendor.

Communicating the change to a vendor may be a subsequent action but is not the standardized first step required by a change management plan after CCB approval.

CCreate a cost estimate for the change.

A cost estimate is developed as part of the change request analysis before CCB approval, not after the change has already been approved.

DUpdate the WBS.Correct

The Work Breakdown Structure is the foundational decomposition of all authorized project scope, so any approved scope change must be reflected in the WBS to keep it current and accurate. Updating the WBS ensures the project baseline is realigned and all downstream planning artifacts such as schedules and cost estimates remain consistent. According to PMI standards, an approved scope change triggers an update to the scope baseline, of which the WBS is a key component.

Concept tested: Approved scope change WBS update requirement

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#change management#WBS#scope change#change control board

Community Discussion

No community discussion yet for this question.

Full GSLC Practice