揘eeds?and 搒takeholder engagement approach?are the inputs to which task in the elicitation and collaboration knowledge area?
The correct answer is D. Prepare for elicitation. Prepare for Elicitation (D) is correct because this task uses Needs (to understand what information must be gathered) and the Stakeholder Engagement Approach (to determine how and with whom to engage) to plan and scope elicitation activities before they begin - both are…
Question
揘eeds?and 搒takeholder engagement approach?are the inputs to which task in the elicitation and collaboration knowledge area?
Options
- AElicitation analysis
- BConduct elicitation
- CStakeholder collaboration
- DPrepare for elicitation
How the community answered
(19 responses)- B5% (1)
- C5% (1)
- D89% (17)
Explanation
Prepare for Elicitation (D) is correct because this task uses Needs (to understand what information must be gathered) and the Stakeholder Engagement Approach (to determine how and with whom to engage) to plan and scope elicitation activities before they begin - both are explicitly listed as inputs in BABOK v3.
Why the distractors are wrong:
- A (Elicitation Analysis) is not a recognized BABOK task name in this knowledge area, making it an invalid option.
- B (Conduct Elicitation) receives the Elicitation Activity Plan (an output of Prepare for Elicitation) as its key input, not Needs or the engagement approach directly.
- C (Stakeholder Collaboration / Manage Stakeholder Collaboration) takes the Stakeholder Engagement Approach as an input, but not Needs - and its focus is on ongoing relationship management, not planning what to elicit.
Memory tip: Think of it sequentially - you must prepare before you conduct. "Needs" tells you what to elicit, and the "Stakeholder Engagement Approach" tells you who and how - both are planning inputs that belong in the Prepare task, before any actual elicitation happens.