ECBA · Question #139
In which state should elicitation results be in order to begin modelling of requirements?
The correct answer is B. Any. Elicitation Results (any state): modelling can begin with any elicitation result and may lead to the need for more elicitation to clarify or expand upon requirements. Elicitation and modelling may occur sequentially, iteratively, or concurrently.
Elicitation and Collaboration
Question
In which state should elicitation results be in order to begin modelling of requirements?
Options
- AUnconfirmed
- BAny
- CConfirmed
- DDocumented
How the community answered
(48 responses)- A4% (2)
- B94% (45)
- C2% (1)
Explanation
Elicitation Results (any state): modelling can begin with any elicitation result and may lead to the need for more elicitation to clarify or expand upon requirements. Elicitation and modelling may occur sequentially, iteratively, or concurrently.
Topics
#elicitation results state#requirements modelling#elicitation outputs
Community Discussion
No community discussion yet for this question.