IIBA
ECBA · Question #3
Which input is used to prepare for elicitation?
The correct answer is C. Stakeholder engagement approach. Stakeholder Engagement Approach: understanding stakeholders' communication and collaboration needs helps plan and prepare appropriate and effective elicitation events.
Elicitation and Collaboration
Question
Which input is used to prepare for elicitation?
Options
- AActivity plan
- BBusiness analysis information
- CStakeholder engagement approach
- DChange strategy
How the community answered
(57 responses)- A5% (3)
- B2% (1)
- C89% (51)
- D4% (2)
Explanation
Stakeholder Engagement Approach: understanding stakeholders' communication and collaboration needs helps plan and prepare appropriate and effective elicitation events.
Topics
#elicitation preparation#stakeholder engagement approach#prepare for elicitation#inputs
Community Discussion
No community discussion yet for this question.