IIBA
ECBA · Question #58
Which of the following is an input to the prepare for elicitation task?
The correct answer is C. Potential value. The inputs are Needs and Stakeholder Engagement Approach. Potential Value is in category Guidelines and Tools.
Elicitation and Collaboration
Question
Which of the following is an input to the prepare for elicitation task?
Options
- AElicitation activity plan
- BSet up logistics
- CPotential value
- DNeeds
How the community answered
(33 responses)- A3% (1)
- C91% (30)
- D6% (2)
Explanation
The inputs are Needs and Stakeholder Engagement Approach. Potential Value is in category Guidelines and Tools.
Topics
#prepare for elicitation#elicitation inputs#potential value#elicitation planning