The correct answer is B. Delayed approvals. Business analysts continually monitor for such risks as: - stakeholders being diverted to other work, - elicitation activities not providing the quality of business analysis information required, and - delayed approvals.
Question
What is a risk that business analysts (BAs) look for when managing stakeholder engagement?
Options
- AScope creep
- BDelayed approvals
- CInaccurate cost estimated
- DResource shortfalls
Explanation
Business analysts continually monitor for such risks as: - stakeholders being diverted to other work, - elicitation activities not providing the quality of business analysis information required, and - delayed approvals.