ECBA · Question #24

ECBA Question #24: Real Exam Question with Answer & Explanation

The correct answer is B. Delayed approvals. Business analysts continually monitor for such risks as: - stakeholders being diverted to other work, - elicitation activities not providing the quality of business analysis information required, and - delayed approvals.

Question

What is a risk that business analysts (BAs) look for when managing stakeholder engagement?

Options

  • AScope creep
  • BDelayed approvals
  • CInaccurate cost estimated
  • DResource shortfalls

Explanation

Business analysts continually monitor for such risks as: - stakeholders being diverted to other work, - elicitation activities not providing the quality of business analysis information required, and - delayed approvals.