nerdexam
CompTIACompTIA

CV0-004 · Question #321

CV0-004 Question #321: Real Exam Question with Answer & Explanation

The correct answer is C: Compromise. By negotiating a middle ground, the PM used compromise as a conflict resolution technique. Force and avoid do not build consensus, while smoothing minimizes issues but does not resolve them. Compromise achieves agreement acceptable to both sides.

DevOps fundamentals

Question

During a phase review, two stakeholders discuss the approval of a deliverable. The project manager convinces the stakeholders to agree on a common solution. Which of the following best describes what the project manager did to gain approval from both stakeholders?

Options

  • AForce
  • BSmooth
  • CCompromise
  • DAvoid

Explanation

By negotiating a middle ground, the PM used compromise as a conflict resolution technique. Force and avoid do not build consensus, while smoothing minimizes issues but does not resolve them. Compromise achieves agreement acceptable to both sides.

Topics

#Project Management#Stakeholder Management#Conflict Resolution#Communication

Community Discussion

No community discussion yet for this question.

Full CV0-004 PracticeBrowse All CV0-004 Questions