CV0-004 · Question #308
The project manager must create a project charter. Which of the following should be included in the charter?
The correct answer is D. Stakeholder identification. The project charter is a high-level authorization document that outlines the purpose, objectives, and identifies key stakeholders. It does not contain detailed schedules, risk management plans, or resource allocation -- those come later in the planning process.
Question
The project manager must create a project charter. Which of the following should be included in the charter?
Options
- AProject schedule
- BResource allocation
- CRisk plan
- DStakeholder identification
How the community answered
(25 responses)- A4% (1)
- B4% (1)
- D92% (23)
Explanation
The project charter is a high-level authorization document that outlines the purpose, objectives, and identifies key stakeholders. It does not contain detailed schedules, risk management plans, or resource allocation -- those come later in the planning process.
Topics
Community Discussion
No community discussion yet for this question.