CV0-004 · Question #307
A project stakeholder has asked the project manager to provide the performance data of a project. Which of the following should the project manager send to the stakeholder?
The correct answer is B. Dashboard. A dashboard provides visual, real-time performance data such as KPIs, budget usage, and progress toward deliverables. This helps stakeholders quickly interpret project health. Milestones only show schedule checkpoints, and issue logs track problems, not overall performance.
Question
A project stakeholder has asked the project manager to provide the performance data of a project. Which of the following should the project manager send to the stakeholder?
Options
- AIssue log
- BDashboard
- CWBS
- DMilestone chart
How the community answered
(32 responses)- B91% (29)
- C3% (1)
- D6% (2)
Explanation
A dashboard provides visual, real-time performance data such as KPIs, budget usage, and progress toward deliverables. This helps stakeholders quickly interpret project health. Milestones only show schedule checkpoints, and issue logs track problems, not overall performance.