A project stakeholder has asked the project manager to provide the performance data of a project. Which of the following should the project manager send to the stakeholder?

The correct answer is B. Dashboard. A dashboard provides visual, real-time performance data such as KPIs, budget usage, and progress toward deliverables. This helps stakeholders quickly interpret project health. Milestones only show schedule checkpoints, and issue logs track problems, not overall performance.

DevOps fundamentals

Question

A project stakeholder has asked the project manager to provide the performance data of a project. Which of the following should the project manager send to the stakeholder?

Options

  • AIssue log
  • BDashboard
  • CWBS
  • DMilestone chart

How the community answered

(32 responses)
  • B
    91% (29)
  • C
    3% (1)
  • D
    6% (2)

Explanation

A dashboard provides visual, real-time performance data such as KPIs, budget usage, and progress toward deliverables. This helps stakeholders quickly interpret project health. Milestones only show schedule checkpoints, and issue logs track problems, not overall performance.

Topics

#Project management#Stakeholder communication#Performance reporting#Dashboards