CV0-004 · Question #320
A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?
The correct answer is D. Defect log. A defect log specifically tracks bugs, errors, or defects discovered in the product. It includes descriptions, severity, and resolution. Issue logs capture broader non-technical challenges, while change logs and risk registers serve different purposes.
Question
A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?
Options
- AChange log
- BIssue log
- CRisk register
- DDefect log
How the community answered
(50 responses)- A8% (4)
- B2% (1)
- C4% (2)
- D86% (43)
Explanation
A defect log specifically tracks bugs, errors, or defects discovered in the product. It includes descriptions, severity, and resolution. Issue logs capture broader non-technical challenges, while change logs and risk registers serve different purposes.