A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?

The correct answer is D. Defect log. A defect log specifically tracks bugs, errors, or defects discovered in the product. It includes descriptions, severity, and resolution. Issue logs capture broader non-technical challenges, while change logs and risk registers serve different purposes.

DevOps fundamentals

Question

A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?

Options

  • AChange log
  • BIssue log
  • CRisk register
  • DDefect log

How the community answered

(50 responses)
  • A
    8% (4)
  • B
    2% (1)
  • C
    4% (2)
  • D
    86% (43)

Explanation

A defect log specifically tracks bugs, errors, or defects discovered in the product. It includes descriptions, severity, and resolution. Issue logs capture broader non-technical challenges, while change logs and risk registers serve different purposes.