A project manager is taking notes along with gathering feedback about a prior project in order to consider known issues with a project enhancement. Which of the following best describes the plan…
The correct answer is B. A plan for avoiding potential issues that may arise during project execution. The scenario describes a project manager collecting lessons learned from a prior project to anticipate and avoid known issues in a future project enhancement. This is a risk management activity - specifically, creating a risk avoidance or risk mitigation plan by applying…
Question
A project manager is taking notes along with gathering feedback about a prior project in order to consider known issues with a project enhancement. Which of the following best describes the plan that the project team is working on?
Options
- AA plan for capturing issues and conflicts in a project's knowledge base
- BA plan for avoiding potential issues that may arise during project execution
- CA plan for documenting the outcomes of the project
- DA plan for addressing and resolving identified issues once the project has been completed
How the community answered
(27 responses)- B89% (24)
- C4% (1)
- D7% (2)
Explanation
The scenario describes a project manager collecting lessons learned from a prior project to anticipate and avoid known issues in a future project enhancement. This is a risk management activity - specifically, creating a risk avoidance or risk mitigation plan by applying historical knowledge. Option A describes a knowledge base or issue log. Option C describes a project closure or outcomes document. Option D describes a corrective action or issue resolution plan for after a problem occurs. Option B - a plan for avoiding potential issues during project execution - best fits because the team is proactively using past experience to prevent future problems before they happen.