nerdexam
CompTIACompTIA

CV0-004 · Question #319

CV0-004 Question #319: Real Exam Question with Answer & Explanation

The correct answer is B: A plan for avoiding potential issues that may arise during project execution. {"question_number": 10, "correct_answer": "B", "explanation": "The scenario describes a project manager collecting lessons learned from a prior project to anticipate and avoid known issues in a future project enhancement. This is a risk management activity - specifically, creatin

Operations

Question

A project manager is taking notes along with gathering feedback about a prior project in order to consider known issues with a project enhancement. Which of the following best describes the plan that the project team is working on?

Options

  • AA plan for capturing issues and conflicts in a project's knowledge base
  • BA plan for avoiding potential issues that may arise during project execution
  • CA plan for documenting the outcomes of the project
  • DA plan for addressing and resolving identified issues once the project has been completed

Explanation

{"question_number": 10, "correct_answer": "B", "explanation": "The scenario describes a project manager collecting lessons learned from a prior project to anticipate and avoid known issues in a future project enhancement. This is a risk management activity - specifically, creating a risk avoidance or risk mitigation plan by applying historical knowledge. Option A describes a knowledge base or issue log. Option C describes a project closure or outcomes document. Option D describes a corrective action or issue resolution plan for after a problem occurs. Option B - a plan for avoiding potential issues during project execution - best fits because the team is proactively using past experience to prevent future problems before they happen.", "generated_by": "claude-sonnet", "llm_judge_score": 4}

Topics

#Lessons learned#Proactive planning#Issue avoidance#Project enhancement

Community Discussion

No community discussion yet for this question.

Full CV0-004 PracticeBrowse All CV0-004 Questions