A project manager is reviewing quality planning techniques. Which of the following involves comparing results of similar activities?

The correct answer is C. Benchmarking. Benchmarking is a quality technique that compares results, processes, or best practices from similar activities or organizations. It helps set realistic performance standards and identify improvement opportunities. Unlike cost-benefit analysis (financial), benchmarking focuses…

Operations

Question

A project manager is reviewing quality planning techniques. Which of the following involves comparing results of similar activities?

Options

  • APerforming a cost-benefit analysis
  • BDefining metrics
  • CBenchmarking
  • DBrainstorming

How the community answered

(20 responses)
  • B
    5% (1)
  • C
    95% (19)

Explanation

Benchmarking is a quality technique that compares results, processes, or best practices from similar activities or organizations. It helps set realistic performance standards and identify improvement opportunities. Unlike cost-benefit analysis (financial), benchmarking focuses on performance comparison.

Topics

#Quality Planning#Benchmarking#Project Management