CV0-004 · Question #313
A project manager is reviewing quality planning techniques. Which of the following involves comparing results of similar activities?
The correct answer is C. Benchmarking. Benchmarking is a quality technique that compares results, processes, or best practices from similar activities or organizations. It helps set realistic performance standards and identify improvement opportunities. Unlike cost-benefit analysis (financial), benchmarking focuses…
Question
A project manager is reviewing quality planning techniques. Which of the following involves comparing results of similar activities?
Options
- APerforming a cost-benefit analysis
- BDefining metrics
- CBenchmarking
- DBrainstorming
How the community answered
(20 responses)- B5% (1)
- C95% (19)
Explanation
Benchmarking is a quality technique that compares results, processes, or best practices from similar activities or organizations. It helps set realistic performance standards and identify improvement opportunities. Unlike cost-benefit analysis (financial), benchmarking focuses on performance comparison.
Topics
Community Discussion
No community discussion yet for this question.