nerdexam
CompTIA

CV0-004 · Question #312

A project manager is assigned to a project that has contracted with vendors. Which of the following actions should the project manager most frequently take? (Select two).

The correct answer is C. Validate the status report D. Monitor performance. When managing vendor contracts, the PM must validate vendor status reports to confirm progress and monitor vendor performance against agreed service levels. Approving deliverables occurs less frequently, and creating charters/baselining schedules are initiation tasks, not recurri

Operations

Question

A project manager is assigned to a project that has contracted with vendors. Which of the following actions should the project manager most frequently take? (Select two).

Options

  • AUpdate the issue log
  • BCreate a project charter
  • CValidate the status report
  • DMonitor performance
  • EApprove deliverables
  • FBaseline the project schedule

How the community answered

(23 responses)
  • A
    4% (1)
  • C
    78% (18)
  • E
    13% (3)
  • F
    4% (1)

Explanation

When managing vendor contracts, the PM must validate vendor status reports to confirm progress and monitor vendor performance against agreed service levels. Approving deliverables occurs less frequently, and creating charters/baselining schedules are initiation tasks, not recurring vendor management tasks.

Topics

#Project Management#Vendor Management#Performance Monitoring#Status Reporting

Community Discussion

No community discussion yet for this question.

Full CV0-004 Practice