Before confirming an anticipated completion date with the customer, it is MOST important to

The correct answer is C. ensure no components are backordered. See the full explanation below for the reasoning.

AV Installation

Question

Before confirming an anticipated completion date with the customer, it is MOST important to

Options

  • Adouble check the floor finishes.
  • Bensure the date is not a holiday.
  • Censure no components are backordered.
  • Dcreate the system maintenance schedule.

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    75% (15)
  • D
    15% (3)

Topics

#project scheduling#backorder management#procurement#completion dates