CTS · Question #8

A client has ordered a large project from a company. This project has several critical components and a fixed schedule. Which of the following will be VITAL for ensuring that the company meets the…

The correct answer is B. confirming lead times. See the full explanation below for the reasoning.

AV Installation

Question

A client has ordered a large project from a company. This project has several critical components and a fixed schedule. Which of the following will be VITAL for ensuring that the company meets the deadlines?

Options

  • Aproper job costing
  • Bconfirming lead times
  • Cqualifying the customer
  • Dconfirming price changes

How the community answered

(37 responses)
  • A
    14% (5)
  • B
    76% (28)
  • C
    8% (3)
  • D
    3% (1)

Topics

#lead times#project scheduling#procurement#supply chain