Which of the following is addressed within the Needs Analysis part of the AV Design process?

The correct answer is D. identifying functional requirements of the project. See the full explanation below for the reasoning.

Audiovisual Design

Question

Which of the following is addressed within the Needs Analysis part of the AV Design process?

Options

  • Acreating the project timeline
  • Boutlining project Bill of Materials
  • Cidentifying key stakeholders for the project
  • Didentifying functional requirements of the project

How the community answered

(47 responses)
  • A
    13% (6)
  • B
    4% (2)
  • C
    9% (4)
  • D
    74% (35)

Topics