Which of the following is addressed within the Needs Analysis part of the AV Design process?
The correct answer is D. identifying functional requirements of the project. See the full explanation below for the reasoning.
Audiovisual Design
Question
Which of the following is addressed within the Needs Analysis part of the AV Design process?
Options
- Acreating the project timeline
- Boutlining project Bill of Materials
- Cidentifying key stakeholders for the project
- Didentifying functional requirements of the project
How the community answered
(47 responses)- A13% (6)
- B4% (2)
- C9% (4)
- D74% (35)
Topics
#needs analysis#functional requirements#AV design process#stakeholder identification