nerdexam
iSQI

CTFL_SYLL_4.0 · Question #152

During iteration planning, a scrum team uses an estimation technique called planning poker to estimate the effort required to deliver a critical user story. In advance of the estimation session, the…

The correct answer is D. the team discusses the differences in the estimates and repeats the poker round until an. In a planning poker session, if there is a significant difference in the estimations, it indicates that there may be misunderstandings or different perspectives on the complexity of the user story. According to the agile principles, the team should discuss these differences to…

Managing the Test Activities

Question

During iteration planning, a scrum team uses an estimation technique called planning poker to estimate the effort required to deliver a critical user story. In advance of the estimation session, the team agreed on some ground rules to limit the number of poker rounds and save time. The team agreed on the following: 1. They will use the following progression for estimation: Extra-small, Small, Medium, Large, Extra- large, and Extra-extra-large. 2. If estimation values differ significantly, the highest score will be used for estimation purposes. The result of the first round of planning poker: Team Member Estimation Business Large Development Extra-extra-large Testing Extra-extra-large Which of the following options best represent the team's next actions?

Options

  • AThe fact that all estimations are high indicate that the user story is not well understood or should
  • BThe pre-agreed rules state that the highest score should be used for estimation, resulting in the
  • CSince the business representative is likely to have the most informed view of the requirement, the
  • Dthe team discusses the differences in the estimates and repeats the poker round until an

How the community answered

(71 responses)
  • A
    4% (3)
  • B
    13% (9)
  • C
    6% (4)
  • D
    77% (55)

Explanation

In a planning poker session, if there is a significant difference in the estimations, it indicates that there may be misunderstandings or different perspectives on the complexity of the user story. According to the agile principles, the team should discuss these differences to reach a common understanding. The goal is to ensure that all team members have a shared understanding of the user story's scope and complexity before finalizing the estimate.

Topics

#planning poker#Agile estimation#iteration planning#estimation rules

Community Discussion

No community discussion yet for this question.

Full CTFL_SYLL_4.0 Practice