You are working on calculating the estimation for a project. You have been given the following numbers by your manager, who is considered to be an expert in estimation: Optimistic = 35 days Likely =…

The correct answer is D. E is 43.3 days, SD = 5. Option D is correct because it correctly applies the PERT three-point estimation formulas: E = (O + 4M + P) / 6 = (35 + 4×40 + 65) / 6 = 260 / 6 = 43.3 days SD = (P − O) / 6 = (65 − 35) / 6 = 5 Why the distractors are wrong: A (E=46.3, SD=35) - Both values are wrong; SD=35 is…

Managing the Test Activities

Question

You are working on calculating the estimation for a project. You have been given the following numbers by your manager, who is considered to be an expert in estimation:

Optimistic = 35 days Likely = 40 days Pessimistic = 65 days Apply the three-point estimation technique, what is the proper expression of the final estimate?

Options

  • AE is 46.3 days, SD = 35
  • BE is 40 days, SD = 6.67
  • CE is 37.3 days, SD = 43.3
  • DE is 43.3 days, SD = 5

How the community answered

(29 responses)
  • A
    10% (3)
  • B
    17% (5)
  • C
    3% (1)
  • D
    69% (20)

Explanation

Option D is correct because it correctly applies the PERT three-point estimation formulas:

  • E = (O + 4M + P) / 6 = (35 + 4×40 + 65) / 6 = 260 / 6 = 43.3 days
  • SD = (P − O) / 6 = (65 − 35) / 6 = 5

Why the distractors are wrong:

  • A (E=46.3, SD=35) - Both values are wrong; SD=35 is just the Optimistic value, not a deviation calculation.
  • B (E=40, SD=6.67) - E=40 is simply the Most Likely value with no weighting applied; SD=6.67 doesn't follow the correct formula either (looks like 40/6).
  • C (E=37.3, SD=43.3) - Both values are nonsensical; the SD cannot be larger than the range of estimates, and E is lower than the Optimistic value.

Memory tip: Remember the formula as "the 4 goes to the middle" - 4× the Most Likely value is the key weight because it represents the most probable outcome. For SD, think "Pessimistic minus Optimistic, divided by 6" - it measures how spread out (uncertain) your estimate is.