Question

You are working on calculating the estimation for a project. You have been given the following numbers by your manager, who is considered to be an expert in estimation: Optimistic = 35 days Likely = 40 days Pessimistic = 65 days Apply the three-point estimation technique, what is the proper expression of the final estimate?

Options

  • AE is 46.3 days, SD = 35
  • BE is 40 days, SD = 6.67
  • CE is 37.3 days, SD = 43.3
  • DE is 43.3 days, SD = 5

Unlock CTFL_SYLL_4.0 to see the answer