CTFL_SYLL_4.0 · Question #151

During which main group of test activity are the following tasks performed? - Checking test results and logs against specified coverage criteria. - Assessing the level of component or system quality…

The correct answer is D. Test monitoring and control. The activities of checking test results and logs against specified coverage criteria, assessing the level of component or system quality based on test results and logs, and determining whether more tests are needed fall under the category of test monitoring and control. This…

Managing the Test Activities

Question

During which main group of test activity are the following tasks performed?

  • Checking test results and logs against specified coverage criteria.
  • Assessing the level of component or system quality based on test

results and logs.

  • Determining whether more tests are needed.

Select the correct answer:

Options

  • ATest planning.
  • BTest analysis.
  • CTest design.
  • DTest monitoring and control.

How the community answered

(55 responses)
  • A
    2% (1)
  • B
    7% (4)
  • C
    4% (2)
  • D
    87% (48)

Explanation

The activities of checking test results and logs against specified coverage criteria, assessing the level of component or system quality based on test results and logs, and determining whether more tests are needed fall under the category of test monitoring and control. This phase involves ongoing assessment and adjustment of the test activities to ensure they meet the test objectives and quality goals.

Topics

#test monitoring and control#coverage criteria#test activities#quality assessment