CTAL-TM_UK · Question #27
A chart showing the trend in the lag time from defect reporting to resolution during system testing is also available. The chart shows that the daily closure period is consistently and significantly…
The correct answer is B. The defect management process. See the full explanation below for the reasoning.
Question
A chart showing the trend in the lag time from defect reporting to resolution during system testing is also available. The chart shows that the daily closure period is consistently and significantly above the rolling closure period for a long period of the system testing phase. Almost all defects found during system testing have been related to the system as a whole, not related to single units or integrations issues. Almost all quality risks have been addressed during the unit and integration testing phase and no residual quality risks were present in the integrated system. This has been confirmed by exploratory testing sessions performed during system testing, targeted at finding defects in these quality risk areas. Based on the given information only, which one of the following areas would you expect to be considered more in the retrospective meeting in order to be improved?
Options
- AThe requirements review
- BThe defect management process
- CThe quality risk analysis process
- DThe system design and architecture design reviews
How the community answered
(41 responses)- A2% (1)
- B73% (30)
- C17% (7)
- D7% (3)