Question

Assume that you are the Test Manager for a small insurance application development project. You have decided to adopt a risk-based testing strategy: 5 product risks (R1, R2, R3, R4, R5) have been identified and their levels of risk have been assessed. 10 test cases (T1, ..., T10) have been designed to cover all the product risks. The following table shows the risk level and the test cases associated to the identified product risks (higher risk level means higher risk): You are not confident with the assessment of the risk level and you suspect that it will be possible to find high-priority bugs in low-risk areas. Furthermore the period for test execution is very short. Your goal is to test all the product risks in a risk-based way, while assuring that each product risk gets at least some amount of testing. Which of the following answers describes the best test execution schedule in this scenario?

Exhibit

CTAL-TM_UK question #58 exhibit

Options

  • AT1, T2, T3, T4, T5, T6, T7, T8, T9, T10
  • BT1, T3, T5, T7, T9, T2, T4, T6, T8, T10
  • CT10, T9, T8, T7, T6, T5, T4, T3, T2, T1
  • DT10, T8, T6, T4, T2, T9, T7, T5, T3, T1