CTAL-TM_001 · Question #56
Which one of the following estimation approaches is appropriate at this stage of the project? 2 credits
The correct answer is A. Create an estimate based on the function point analysis technique and test point analysis. See the full explanation below for the reasoning.
Question
Which one of the following estimation approaches is appropriate at this stage of the project? 2 credits
Options
- ACreate an estimate based on the function point analysis technique and test point analysis
- BCreate an estimate based on the complexity of the code
- CCreate an estimate based on the credentials of the successful bidder
- DCreate an estimate based on a percentage of the development effort
How the community answered
(31 responses)- A74% (23)
- B10% (3)
- C3% (1)
- D13% (4)