Which aspect in the test estimate is the main risk in this project? 1 credit
The correct answer is D. Unknown input quality due to third party development. Topic 8, Scenario 8, V2 "Test Proems Improvement' You have raised the issue that improving the testing process is also dependent on the status of the software development process.
Test Planning and Control
Question
Which aspect in the test estimate is the main risk in this project? 1 credit
Options
- AQuality of the specification
- BAvailability of end-users
- CThe costs of hardware and tools
- DUnknown input quality due to third party development
How the community answered
(23 responses)- A4% (1)
- B4% (1)
- C9% (2)
- D83% (19)
Explanation
Topic 8, Scenario 8, V2 "Test Proems Improvement' You have raised the issue that improving the testing process is also dependent on the status of the software development process.