CTAL-TM_001 · Question #53

Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:

The correct answer is C. c E. e. Topic 10, Scenario 10, V3 "Online Application" The cancellation of a current major development project has released resources. The development manager has decided to respond to his own request to tender and has proposed an in-house development with the use of a Rapid…

Test Planning and Control

Question

Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:

Options

  • Aa
  • Bb
  • Cc
  • Dd
  • Ee
  • Ff
  • GWhich test staff members (names) will be involved and when
  • HLevel of requirements coverage achieved

How the community answered

(40 responses)
  • C
    73% (29)
  • D
    8% (3)
  • F
    13% (5)
  • G
    5% (2)
  • H
    3% (1)

Explanation

Topic 10, Scenario 10, V3 "Online Application" The cancellation of a current major development project has released resources. The development manager has decided to respond to his own request to tender and has proposed an in-house development with the use of a Rapid Application Development (RAO) approach.

Topics

#master test plan#phase test plan#test planning#test documentation

Community Discussion

No community discussion yet for this question.