The development manager is managing the review of the responses received from bidders, and has asked the in-house test manager to provide a review checklist for the test management aspects of the…

The correct answer is D. The bidder's project test plan depicts a phased implementation with later delivery dates to be. iSQI CTAL-TM_001 Exam

Test Management

Question

The development manager is managing the review of the responses received from bidders, and has asked the in-house test manager to provide a review checklist for the test management aspects of the responses. Which of the following checkpoints would be appropriate? 2 credits

Options

  • AThe bidder's test policy should enforce that incident management fully conforms to IEEE 1044.
  • BThe bidder's project strategy shows that the data content of all the test environments conforms
  • CThe bidder's test plan shows that the application will be delivered for acceptance in six months
  • DThe bidder's project test plan depicts a phased implementation with later delivery dates to be

How the community answered

(50 responses)
  • A
    6% (3)
  • B
    4% (2)
  • C
    10% (5)
  • D
    80% (40)

Explanation

iSQI CTAL-TM_001 Exam

Topics

#test management review#vendor assessment#test plan evaluation#phased delivery

Community Discussion

No community discussion yet for this question.

Full CTAL-TM_001 Practice