Which of the following is a project risk mitigation step you might take as test manager? 1 credit

The correct answer is C. Arranging a back-up test environment in case the existing one fails during testing. Topic 5, Scenario 5, V2 "Human Resource System" For the first increment of the new enterprise HR product you have performed a product risk iSQI CTAL-TM_001 Exam analysis using the FMEA method. Five risk items have been identified and the likelihood and impact have been scored…

Test Management

Question

Which of the following is a project risk mitigation step you might take as test manager? 1 credit

Exhibit

CTAL-TM_001 question #24 exhibit

Options

  • ATesting for performance problems
  • BHiring a contractor after a test analyst leaves the company
  • CArranging a back-up test environment in case the existing one fails during testing
  • DPerforming a project retrospective meeting using the test results after each increment

How the community answered

(34 responses)
  • A
    12% (4)
  • B
    9% (3)
  • C
    76% (26)
  • D
    3% (1)

Explanation

Topic 5, Scenario 5, V2 "Human Resource System" For the first increment of the new enterprise HR product you have performed a product risk iSQI CTAL-TM_001 Exam analysis using the FMEA method. Five risk items have been identified and the likelihood and impact have been scored using scoring tables. This has resulted in the following scores:

Topics

#project risk mitigation#test management#risk response#test environment