CTAL-TM_001 · Question #23
Which of the following is least likely to be used as a technique to identify project and product risks? 1 credit
The correct answer is B. Inspections. See the full explanation below for the reasoning.
Question
Which of the following is least likely to be used as a technique to identify project and product risks? 1 credit
Options
- ABrainstorming
- BInspections
- CExpert interviews
- DIndependent assessments
How the community answered
(41 responses)- A2% (1)
- B83% (34)
- C5% (2)
- D10% (4)