A unit level test plan should be input to a system or integration level test plan.
The correct answer is A. True. See the full explanation below for the reasoning.
Question
A unit level test plan should be input to a system or integration level test plan.
Options
- ATrue
- BFalse
How the community answered
(44 responses)- A73% (32)
- B27% (12)
Community Discussion