Which of the following are negative possibilities if quality requirements are not met?

The correct answer is C. Overworking team members and poor product quality. See the full explanation below for the reasoning.

Question

Which of the following are negative possibilities if quality requirements are not met?

Options

  • ATermination
  • BCustomer complaints and late product
  • COverworking team members and poor product quality
  • DPoor quality

How the community answered

(24 responses)
  • A
    17% (4)
  • B
    8% (2)
  • C
    71% (17)
  • D
    4% (1)