CSSBB · Question #144

A team wants to make a schedule for a project showing which tasks must be done sequentially and which may be done simultaneously. Which tool is most appropriate?

The correct answer is E. activity network diagram. See the full explanation below for the reasoning.

Define Phase

Question

A team wants to make a schedule for a project showing which tasks must be done sequentially and which may be done simultaneously. Which tool is most appropriate?

Options

  • Amatrix diagram
  • Bcause and effect diagram
  • Cprocess decision program chart
  • Daffinity diagram
  • Eactivity network diagram
  • Ftree diagram
  • Gprioritization matrix
  • Hmatrix diagram

How the community answered

(32 responses)
  • A
    6% (2)
  • B
    3% (1)
  • E
    84% (27)
  • F
    6% (2)

Topics

#activity network diagram#7 MP tools#project scheduling#concurrent tasks