CSAPM · Question #81

Agile performance indicators show improvement, yet executives reduce support. What is the most likely CSAPM explanation?

The correct answer is B. Metrics optimize delivery, not strategic value. Senior leaders care about strategic impact, not operational improvement alone.

Agile Project Management in Practice

Question

Agile performance indicators show improvement, yet executives reduce support. What is the most likely CSAPM explanation?

Options

  • AExecutives misunderstand agile metrics
  • BMetrics optimize delivery, not strategic value
  • CTeams manipulate the metrics
  • DAgile maturity is still low

How the community answered

(40 responses)
  • A
    10% (4)
  • B
    57% (23)
  • C
    8% (3)
  • D
    25% (10)

Explanation

Senior leaders care about strategic impact, not operational improvement alone.

Topics

#agile metrics#strategic value#executive alignment#organizational agility