Which metric is most dangerous when used at senior management level?

The correct answer is C. Velocity. Velocity misuse drives local optimization and manipulation-this is a classic CSAPM trap.

Agile Project Management in Practice

Question

Which metric is most dangerous when used at senior management level?

Options

  • ALead time
  • BCustomer satisfaction
  • CVelocity
  • DBenefits realization

How the community answered

(53 responses)
  • A
    11% (6)
  • B
    6% (3)
  • C
    81% (43)
  • D
    2% (1)

Explanation

Velocity misuse drives local optimization and manipulation-this is a classic CSAPM trap.

Topics

#velocity misuse#agile metrics#management reporting#measuring agility