Which metric is most dangerous when used at senior management level?
The correct answer is C. Velocity. Velocity misuse drives local optimization and manipulation-this is a classic CSAPM trap.
Agile Project Management in Practice
Question
Which metric is most dangerous when used at senior management level?
Options
- ALead time
- BCustomer satisfaction
- CVelocity
- DBenefits realization
How the community answered
(53 responses)- A11% (6)
- B6% (3)
- C81% (43)
- D2% (1)
Explanation
Velocity misuse drives local optimization and manipulation-this is a classic CSAPM trap.
Topics
#velocity misuse#agile metrics#management reporting#measuring agility