IAPM
CSAPM · Question #17
Agile contracts fail when they primarily focus on:
The correct answer is B. Risk transfer. Risk transfer breaks partnership-a subtle but common exam point.
Agile Project Management in Practice
Question
Agile contracts fail when they primarily focus on:
Options
- ACost control
- BRisk transfer
- CCollaboration
- DFlexibility
How the community answered
(59 responses)- A19% (11)
- B66% (39)
- C5% (3)
- D10% (6)
Explanation
Risk transfer breaks partnership-a subtle but common exam point.
Topics
#agile contracts#risk transfer#collaboration-based contracting#vendor relationships
Community Discussion
No community discussion yet for this question.