What is the biggest systemic risk of excessive reporting?

The correct answer is C. Distorted behavior. Reports change behavior; teams optimize for appearance, not value.

Agile Project Management in Practice

Question

What is the biggest systemic risk of excessive reporting?

Options

  • ATime waste
  • BSlower delivery
  • CDistorted behavior
  • DReduced motivation

How the community answered

(27 responses)
  • A
    15% (4)
  • B
    4% (1)
  • C
    74% (20)
  • D
    7% (2)

Explanation

Reports change behavior; teams optimize for appearance, not value.

Topics

#metrics#reporting#behavioral distortion#governance