IAPM
CSAPM · Question #4
A high-performing team consistently bypasses architectural standards to move fast. What should concern a CSAPM most?
The correct answer is B. Increased technical debt at system level. Senior agile focus is system sustainability, not short-term speed.
Agile Project Management in Practice
Question
A high-performing team consistently bypasses architectural standards to move fast. What should concern a CSAPM most?
Options
- AReduced predictability
- BIncreased technical debt at system level
- CLack of discipline
- DNon-compliance with process
How the community answered
(49 responses)- A10% (5)
- B61% (30)
- C24% (12)
- D4% (2)
Explanation
Senior agile focus is system sustainability, not short-term speed.
Topics
#technical debt#architectural governance#system integrity#technical standards