CSAPM · Question #20
Why does adding more coordination layers usually reduce agility?
The correct answer is C. It delays feedback loops. Feedback speed is critical in agile systems.
Agile Project Management in Practice
Question
Why does adding more coordination layers usually reduce agility?
Options
- AIt slows reporting
- BIt increases roles
- CIt delays feedback loops
- DIt increases cost
How the community answered
(32 responses)- A6% (2)
- B22% (7)
- C59% (19)
- D13% (4)
Explanation
Feedback speed is critical in agile systems.
Topics
#coordination layers#feedback loops#organizational design#agility