The correct answer is C. Outcomes and principles are met. CSAPM assesses maturity by outcomes and values, not standardization.

Question

A senior agile manager should tolerate process variance between teams when:

Options

  • ATeams request it
  • BVelocity improves
  • COutcomes and principles are met
  • DDocumentation exists

Explanation

CSAPM assesses maturity by outcomes and values, not standardization.