CSAPM · Question #129
A CSAPM sees teams maximizing velocity while customer value stagnates. What is the root cause?
The correct answer is B. Misused performance metrics. Velocity used as a target becomes dysfunctional.
Agile Project Management in Practice
Question
A CSAPM sees teams maximizing velocity while customer value stagnates. What is the root cause?
Options
- AWrong estimation technique
- BMisused performance metrics
- CInsufficient skills
- DPoor sprint planning
How the community answered
(25 responses)- A4% (1)
- B68% (17)
- C12% (3)
- D16% (4)
Explanation
Velocity used as a target becomes dysfunctional.
Topics
#velocity#agile metrics#customer value#performance measurement