An agile program delivers features regularly, but customer satisfaction decreases. What is the most plausible CSAPM diagnosis?
The correct answer is C. Output is prioritized over outcomes. CSAPM distinguishes clearly between delivering features and delivering value.
Agile Project Management in Practice
Question
An agile program delivers features regularly, but customer satisfaction decreases. What is the most plausible CSAPM diagnosis?
Options
- ATeams lack technical skills
- BDelivery cadence is too fast
- COutput is prioritized over outcomes
- DStakeholder expectations are unrealistic
How the community answered
(40 responses)- A25% (10)
- B10% (4)
- C60% (24)
- D5% (2)
Explanation
CSAPM distinguishes clearly between delivering features and delivering value.
Topics
#outcome vs output#customer satisfaction#value delivery#agile metrics