A CSAPM avoids micro-metrics because they:
The correct answer is C. Distort behavior. You've hit your limit · resets 12:50am (America/New_York)
Agile Project Management in Practice
Question
A CSAPM avoids micro-metrics because they:
Options
- AAre inaccurate
- BTake time
- CDistort behavior
- DReduce visibility
How the community answered
(57 responses)- A4% (2)
- B4% (2)
- C84% (48)
- D9% (5)
Explanation