CRISC · Question #516

Which of the following is a PRIMARY reason for considering existing controls during initial risk assessment?

The correct answer is C. To determine the current risk level. During an initial risk assessment, considering existing controls is crucial to determine the current risk level, also known as residual risk, which is the risk remaining after controls are applied. This provides a realistic view of the organization's present risk posture.

Submitted by ravi_2018· Apr 18, 2026IT Risk Assessment

Question

Which of the following is a PRIMARY reason for considering existing controls during initial risk assessment?

Options

  • ATo determine the inherent risk level
  • BTo determine the acceptable risk level
  • CTo determine the current risk level
  • DTo determine the desired risk level

How the community answered

(40 responses)
  • A
    3% (1)
  • B
    8% (3)
  • C
    88% (35)
  • D
    3% (1)

Why each option

During an initial risk assessment, considering existing controls is crucial to determine the current risk level, also known as residual risk, which is the risk remaining after controls are applied. This provides a realistic view of the organization's present risk posture.

ATo determine the inherent risk level

Inherent risk is the risk level before any controls are considered or applied.

BTo determine the acceptable risk level

Acceptable risk level is a management decision about how much risk the organization is willing to tolerate, not determined by existing controls.

CTo determine the current risk levelCorrect

Considering existing controls during an initial risk assessment allows the practitioner to evaluate the effectiveness of current safeguards and determine the *residual risk*, which is the current risk level after controls have been implemented. This provides a realistic picture of the organization's actual exposure.

DTo determine the desired risk level

Desired risk level is a target for the future, not a measure of the present situation including existing controls.

Concept tested: Risk assessment components (residual risk)

Topics

#Risk assessment process#Current risk#Existing controls#Risk terminology