The PRIMARY focus of an ongoing risk awareness program should be to:

The correct answer is A. enable better risk-based decisions.. The primary focus of an ongoing risk awareness program should be to empower individuals within the organization to make informed, risk-based decisions in their daily activities.

Submitted by tunde_lagos· Apr 18, 2026Governance

Question

The PRIMARY focus of an ongoing risk awareness program should be to:

Options

  • Aenable better risk-based decisions.
  • Bdefine appropriate controls to mitigate risk.
  • Cdetermine impact of risk scenarios.
  • Dexpand understanding of risk indicators.

How the community answered

(27 responses)
  • A
    96% (26)
  • D
    4% (1)

Why each option

The primary focus of an ongoing risk awareness program should be to empower individuals within the organization to make informed, risk-based decisions in their daily activities.

Aenable better risk-based decisions.Correct

An effective risk awareness program aims to educate all personnel about the organization's risk landscape, policies, and their individual role in managing risk. This knowledge enables employees to identify, report, and appropriately respond to risks in their daily operations, directly contributing to better, more informed risk-based decisions across the organization at all levels.

Bdefine appropriate controls to mitigate risk.

Defining controls is typically a function of risk management or security teams, not the primary focus of a general risk awareness program for all employees.

Cdetermine impact of risk scenarios.

Determining the impact of risk scenarios is part of a risk assessment process, usually performed by risk management professionals, not the core goal of a general awareness program.

Dexpand understanding of risk indicators.

While expanding understanding of risk indicators is a component of awareness, it's a means to an end; the ultimate goal is to translate that understanding into better decision-making to manage risks effectively.

Concept tested: Purpose of risk awareness programs

Source: https://csrc.nist.gov/publications/detail/sp/800-50/final