CRISC · Question #340
A risk practitioner wants to identify potential risk events that affect the continuity of a critical business process. Which of the following should the risk practitioner do FIRST?
The correct answer is C. Review the methodology used to conduct the business impact analysis (BIA).. To identify potential risk events affecting the continuity of a critical business process, a risk practitioner should first review the methodology used for the Business Impact Analysis (BIA).
Question
A risk practitioner wants to identify potential risk events that affect the continuity of a critical business process. Which of the following should the risk practitioner do FIRST?
Options
- AEvaluate current risk management alignment with relevant regulations.
- BDetermine if business continuity procedures are reviewed and updated on a regular basis.
- CReview the methodology used to conduct the business impact analysis (BIA).
- DConduct a benchmarking exercise against industry peers.
How the community answered
(41 responses)- A2% (1)
- B5% (2)
- C85% (35)
- D7% (3)
Why each option
To identify potential risk events affecting the continuity of a critical business process, a risk practitioner should first review the methodology used for the Business Impact Analysis (BIA).
Evaluating risk management alignment with regulations is a governance activity, which is not the first step in identifying specific risk events for a particular business process.
Determining if business continuity procedures are reviewed and updated assesses the effectiveness of existing controls, which typically occurs after understanding the risks to continuity.
A Business Impact Analysis (BIA) is specifically designed to identify critical business processes, their dependencies, and the potential impact of their disruption. By reviewing the BIA methodology, the risk practitioner ensures that the foundational analysis of criticality and potential impacts is sound, comprehensive, and up-to-date, thereby providing a robust basis for identifying relevant risk events to business continuity.
Conducting a benchmarking exercise provides external comparison with industry peers but does not directly identify the internal risk events specific to an organization's critical business processes.
Concept tested: Risk identification for business continuity