CRISC · Question #31
Which of the following is a risk practitioner's MOST important responsibility in managing risk acceptance that exceeds risk tolerance?
The correct answer is A. Verify authorization by senior management.. When risk acceptance exceeds tolerance, the risk practitioner's primary duty is to confirm that senior management has formally approved this deviation. This ensures proper governance and accountability for elevated risk levels.
Question
Which of the following is a risk practitioner's MOST important responsibility in managing risk acceptance that exceeds risk tolerance?
Options
- AVerify authorization by senior management.
- BIncrease the risk appetite to align with the current risk level
- CEnsure the acceptance is set to expire over lime
- DUpdate the risk response in the risk register.
How the community answered
(43 responses)- A81% (35)
- B2% (1)
- C5% (2)
- D12% (5)
Why each option
When risk acceptance exceeds tolerance, the risk practitioner's primary duty is to confirm that senior management has formally approved this deviation. This ensures proper governance and accountability for elevated risk levels.
Risk acceptance exceeding tolerance represents a significant deviation from established limits, requiring formal endorsement from senior management or the appropriate risk owner who has the authority to accept such a level of risk. Verifying this authorization ensures that the organization's governance structure acknowledges and takes responsibility for the heightened risk exposure.
Increasing the risk appetite to align with the current risk level is a strategic decision that changes the organization's overall willingness to take on risk, which is not a risk practitioner's primary responsibility in managing a specific risk acceptance.
While setting an expiration for risk acceptance can be a good practice, it is not the MOST important initial responsibility when managing an acceptance that already exceeds tolerance.
Updating the risk response in the risk register is an administrative task that follows the decision-making process, rather than being the most important responsibility during the authorization phase of exceeding tolerance.
Concept tested: Risk acceptance authorization and governance
Topics