CRISC · Question #179

CRISC Question #179: Real Exam Question with Answer & Explanation

The correct answer is A: Assign process owners to key risk areas.. The most effective way to ensure accountability for managing risk is to assign process owners to key risk areas.

Submitted by satoshi_tk· Apr 18, 2026Governance

Question

Which of the following is the MOST effective way to help ensure accountability for managing risk?

Options

  • AAssign process owners to key risk areas.
  • BObtain independent risk assessments.
  • CAssign incident response action plan responsibilities.
  • DCreate accurate process narratives.

Explanation

The most effective way to ensure accountability for managing risk is to assign process owners to key risk areas.

Common mistakes.

  • B. Independent risk assessments provide an objective view of risks but do not inherently establish ongoing accountability for managing them within the organization.
  • C. Assigning incident response responsibilities addresses accountability during an incident, but not the proactive, continuous management of risk.
  • D. Accurate process narratives are important for understanding processes but do not, by themselves, establish who is accountable for the risks within those processes.

Concept tested. Risk accountability

Reference. https://learn.microsoft.com/en-us/azure/cloud-adoption-framework/secure/security-governance-risk-compliance-strategies#risk-management-framework

Topics

#Risk Accountability#Process Ownership#Risk Governance

Community Discussion

No community discussion yet for this question.

Full CRISC PracticeBrowse All CRISC Questions