The two principal measures of failure during risk assessment are which of the following?

The correct answer is A. Failure severity and failure probability. You've hit your session limit · resets 10:20pm (America/New_York)

Life Cycle Reliability Engineering

Question

The two principal measures of failure during risk assessment are which of the following?

Options

  • AFailure severity and failure probability.
  • BFailure analysis and failure effects.
  • CFailure method and failure mode.
  • DFailure mode and failure mechanism.

How the community answered

(43 responses)
  • A
    72% (31)
  • B
    19% (8)
  • C
    7% (3)
  • D
    2% (1)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#risk assessment#failure severity#failure probability#FMEA