CRE · Question #391
The first phase in the operation life history of a population of product units is typically called:
The correct answer is A. Debugging phase. Option A is correct because in reliability engineering's "bathtub curve," the first phase is the early failure (or infant mortality) period, commonly called the debugging phase. During this phase, failure rates are high but decreasing as defective units - those with…
Question
The first phase in the operation life history of a population of product units is typically called:
Options
- ADebugging phase.
- BWear out phase.
- CTransition phase.
- DChance failure phase.
How the community answered
(54 responses)- A83% (45)
- B4% (2)
- C9% (5)
- D4% (2)
Explanation
Option A is correct because in reliability engineering's "bathtub curve," the first phase is the early failure (or infant mortality) period, commonly called the debugging phase. During this phase, failure rates are high but decreasing as defective units - those with manufacturing flaws, assembly errors, or weak components - are identified and removed from service.
Option B (Wear-out phase) is the third and final phase, where failure rates rise again as components reach the end of their designed lifespan due to fatigue, corrosion, and material degradation.
Option D (Chance failure phase) describes the middle phase, where failure rates are low and roughly constant - failures occur randomly, not due to defects or aging.
Option C (Transition phase) is not a standard term in the bathtub curve model and does not correspond to any of the three recognized phases.
Memory tip: Think of "debugging" as what engineers do early in a product's life - they debug bad units out of the population, just like a programmer debugs faulty code at the start of a project. Early → Debug → Fix → then stable operation begins.