A major change in a validated process requires:
The correct answer is C. Change control and potential re-validation. See the full explanation below for the reasoning.
Question
A major change in a validated process requires:
Options
- AApproval but no documentation
- BNo action if risk is low
- CChange control and potential re-validation
- DEngineering notification only
How the community answered
(25 responses)- A12% (3)
- B4% (1)
- C76% (19)
- D8% (2)