A major change in a validated process requires:

The correct answer is C. Change control and potential re-validation. See the full explanation below for the reasoning.

Question

A major change in a validated process requires:

Options

  • AApproval but no documentation
  • BNo action if risk is low
  • CChange control and potential re-validation
  • DEngineering notification only