The correct answer is A. Check the effectiveness of implemented corrective actions. See the full explanation below for the reasoning.

Question

Audit follow-up actions are necessary to:Response:

Options

  • ACheck the effectiveness of implemented corrective actions
  • BReward the audited team
  • CFinalize audit schedules for the next cycle
  • DConduct team-building activities