Which equipment qualification step verifies installation?

The correct answer is B. IQ. IQ (Installation Qualification) verifies that equipment has been properly installed according to manufacturer specifications, design requirements, and applicable regulations - confirming physical setup, utilities, and documentation are in place before operation begins. Why the…

Question

Which equipment qualification step verifies installation?

Options

  • AOQ
  • BIQ
  • CPQ
  • DValidation review

How the community answered

(35 responses)
  • A
    9% (3)
  • B
    83% (29)
  • C
    3% (1)
  • D
    6% (2)

Explanation

IQ (Installation Qualification) verifies that equipment has been properly installed according to manufacturer specifications, design requirements, and applicable regulations - confirming physical setup, utilities, and documentation are in place before operation begins.

Why the distractors are wrong:

  • A (OQ - Operational Qualification): Confirms the equipment operates as intended across its defined range (e.g., temperature, speed) - this comes after installation is verified.
  • C (PQ - Performance Qualification): Demonstrates the equipment consistently performs in real-world production conditions - the final qualification step.
  • D (Validation review): A documentation/oversight activity, not a formal qualification step in the IQ/OQ/PQ sequence.

Memory tip: Think of the acronym order as a story - Install it, Operate it, Prove it works. IQ = "Is it in?" OQ = "Does it operate?" PQ = "Does it perform?"